NTPC-NETRA effluent recycling plant to be commissioned in SeptemberIllustrative image – not actual.
The second stream of the NTPC Energy Technology Research Alliance (NTPC-NETRA) effluent recycling treatment plant at Jhanor-Gandhar station in Bharuch district of Gujarat will be commissioned by 7 September 2018.

The company is setting up an effluent recycling treatment plant to achieve zero liquid discharge and optimize water costs and minimize environmental footprint.

At present, only one stream of the station has been successfully commissioned. At full load operation, NTPC Jhanor-Gandhar (657.39 MW) will generate effluent of 4,500 cu mtr per day.

The recycling treatment has integrated high rate solid contact clarification, submerged Ultra filtration and RO modules technologies to give 125 cu mtr per hour high quality water.

The produced water will be used for Demineral (DM) water production or directly in Cooling Water (CW) make-up in the power station. With new technologies, the plant will have the added advantage of increased resin life, lesser chemical consumption and improved COC in CW system.

The new technology system also suits the wide variety of industrial effluents and maintains the efficiency of plants.