Illustrative image – not actual.
Essar has begun full load trial of the secondary de-dusting system at the Steel Melting Shop-3 (SMS III) complex at SAIL’s Bhilai Steel plant site.
The company has achieved its milestone towards the erection of basic oxygen furnace (BOF).
The BOF comprises three converters of 160 tonne (nominal) and 180 tonne (maximum) capacity, with associated gas cleaning facilities. Three induced draft (ID) fans have been installed to generate suction for conveying the fumes and clean gas.
The load trials of the ID fan station of the secondary de-dusting system started on 7 November 2017.