Illustrative image – not actual.The much talked about Bandra-Worli Sea Link project was inaugurated on 30
June 2009 by Mrs Sonia Gandhi, UPA Chairperson.
However, of the proposed eight lanes only four lanes is available for traffic
flow. The balance four lanes will be available for traffic after six months.
The project launched in 2001, in addition to huge time and cost overruns, has
faced stiff opposition from local fishermen, State government and Central
government and stoppage of work by contractors and sub-contractors on
non-payment of dues in time.
The Sea Link was launched in 2001 by MSRDC to ease the bottleneck at Mahim
during the peak hours caused by north / south bound traffic. The project
involves construction of 8-lane Sea Link freeway from the interchange of Mahim
intersection at the Bandra-end to Worli Sea face on Khan Abdul Ghaffar Khan Road
(KAGK). The Construction of the Sea Link project is divided into five packages
namely:
Package I: A 680 m long flyover at Lovegrove junction at Worli at a cost of
Rs.7.5 crore. A joint venture between Vichare & Co. and JMC Projects were
contractors for the project. A consortium of Sverdrup Asia Ltd., Shrikhande
Consultants Pvt. Ltd., C. Felice & Company, KPMG India Pvt. Ltd., TPG (India)
was the consultant for the project. The flyover was opened for traffic in March
2002.
Package II: A cloverleaf interchange at Mahim intersection. The UP State Bridge
Corporation constructed the project at Rs.42 crore and completed the same in
February 2003.
Package III: An eight-lane solid approach road connecting Mahim interchange with
toll plaza area on Bandra side. This project was executed by Prakash
Construction at an estimated cost of Rs.55 crore and was completed in February
2003.
Package IV: The construction of the eight-lane main sea bridge and toll plaza.
On 29 September 2000, contract was awarded to Hindustan Construction Co. The
contract was valued at Rs.400.23 crore.
Package V: This package covers works relating to improvement of existing KAGK
road covering three junctions namely, INS strata, Thadani Marg and Lovegrove
Junction. BMC has commenced work of laying 3+3 lanes, the package also includes
construction of two flyovers and three foot-over-bridges.
Also See:
Bandra-Worli sea link to be operational by June (23-Mar-09)