Zoom across the city: Bandra-Worli sea link opened to trafficIllustrative image – not actual.

The much talked about Bandra-Worli Sea Link project was inaugurated on 30 June 2009 by Mrs Sonia Gandhi, UPA Chairperson.

However, of the proposed eight lanes only four lanes is available for traffic flow. The balance four lanes will be available for traffic after six months.

The project launched in 2001, in addition to huge time and cost overruns, has faced stiff opposition from local fishermen, State government and Central government and stoppage of work by contractors and sub-contractors on non-payment of dues in time.

The Sea Link was launched in 2001 by MSRDC to ease the bottleneck at Mahim during the peak hours caused by north / south bound traffic. The project involves construction of 8-lane Sea Link freeway from the interchange of Mahim intersection at the Bandra-end to Worli Sea face on Khan Abdul Ghaffar Khan Road (KAGK). The Construction of the Sea Link project is divided into five packages namely:

Package I: A 680 m long flyover at Lovegrove junction at Worli at a cost of Rs.7.5 crore. A joint venture between Vichare & Co. and JMC Projects were contractors for the project. A consortium of Sverdrup Asia Ltd., Shrikhande Consultants Pvt. Ltd., C. Felice & Company, KPMG India Pvt. Ltd., TPG (India) was the consultant for the project. The flyover was opened for traffic in March 2002.

Package II: A cloverleaf interchange at Mahim intersection. The UP State Bridge Corporation constructed the project at Rs.42 crore and completed the same in February 2003.

Package III: An eight-lane solid approach road connecting Mahim interchange with toll plaza area on Bandra side. This project was executed by Prakash Construction at an estimated cost of Rs.55 crore and was completed in February 2003.

Package IV: The construction of the eight-lane main sea bridge and toll plaza. On 29 September 2000, contract was awarded to Hindustan Construction Co. The contract was valued at Rs.400.23 crore.

Package V: This package covers works relating to improvement of existing KAGK road covering three junctions namely, INS strata, Thadani Marg and Lovegrove Junction. BMC has commenced work of laying 3+3 lanes, the package also includes construction of two flyovers and three foot-over-bridges.