Yettinahole irrigation project hits land acquisition barrierIllustrative image – not actual.

The Yettinahole project, which got National Green Tribunal (NGT) clearance in March 2019, has hit 5,278 acre land acquisition hurdle. The project will come up near Doddaballapur in Bengaluru Rural district in Karnataka.

 

The government needs this land to build a reservoir at Byragondlu which will be crucial for ensuring water supply to the outskirts of Bengaluru and surrounding districts. The roadblock is over compensation offered to land owners as per the 2013 Land Acquisition Act, as per which the compensation is up to four times the market value in rural areas.

The proposed reservoir falls under the jurisdiction of two taluks — Doddaballapur in Bengaluru Rural district and Koratagere in Tumakuru district.

The land needed in Koratagere is 2,681 acre and 2,797 acre in Doddaballapur. The Byragondlu reservoir, which will come up at a cost of Rs 592 crore, will provide water to Devanahalli Industrial Area, Chikkaballapur and Kolar districts.

The rest of the districts including Hassan, Chikkamagaluru and Ramanagara will get water through the gravity canal. Following the NGT nod, the government has already issued tenders for gravity canal construction for a stretch of 240 km, out of a total of 260 km. Works have begun at certain parts which is 57 km.

Phase-I of the project is expected to be completed by June 2020. This includes lift component work, taken up at a cost of Rs 3,716.49 crore. There are four streams that come together for lifting water for the project: Yettinahole, Kadumanehole, Kerehole and Vangada halla.

The project is estimated to cater to drinking water needs by providing 24.01 TMC of water to 68.35 lakh people living in seven districts. This apart, 527 micro irrigation tanks will be filled to recharge groundwater levels in these districts.