Yavatmal water supply scheme progressing wellIllustrative image – not actual.
Maharashtra Jeevan Pradhikaran has taken up Yavatmal water supply scheme in Yavatmal district of Maharashtra. As confirmed with Projects Today, around 40 percent work has been completed on the project.

The project with a capacity of 48 MLD is being developed under Atal Mission for Rejuvenation and Urban Transformation (AMRUT).

In 2017, P L Adake secured an order worth Rs 276.13 crore for developing Phase-I and Phase-II of the project and commenced work on the project soon after.

Talking to Projects Today, the promoter disclosed that project work will last for around four years and the scheme will be commissioned in February 2021.