Illustrative image – not actual. Birla Surya, a part of the Yash Birla Group, has chalked out an investment plan to set up an integrated facility for silicon wafers unit.
The company plans to invest $1.2 billion (approx Rs 5,400 crore) over five years to set up an integrated facility for fabrication of multi-crystalline silicon wafers and the processing of solar photovoltaic cells.
The proposed facility will be located at Rajewadi in Satara District in Maharashtra. The company has acquired land for Phase I of the project and is simultaneously acquiring land for expansion. Currently, the civil construction is being carried out by L&T. It has signed contracts with technology suppliers such as Roth & Rau AG of Germany, GT Solar of USA, Herbert Arnold GmbH & Co. KG of Germany and RENA GmbH of Germany. The manufacturing facility will be for 60 MWp (megawatt peak) of multi-crystalline solar photovoltaic cells and fabrication of 125 MWp multi-crystalline silicon wafers using solar grade silicon. Phase I is slated to be commissioned by December 2011.
Phase I of the project will entail an investment of Rs 1,493 crore which is to be funded through a debt of Rs 970 crore. Asia Pacific Capital will invest $15 million (approx Rs 68 Crore) as private equity in the project.
Related Links:
Project profile
The company plans to invest $1.2 billion (approx Rs 5,400 crore) over five years to set up an integrated facility for fabrication of multi-crystalline silicon wafers and the processing of solar photovoltaic cells.
The proposed facility will be located at Rajewadi in Satara District in Maharashtra. The company has acquired land for Phase I of the project and is simultaneously acquiring land for expansion. Currently, the civil construction is being carried out by L&T. It has signed contracts with technology suppliers such as Roth & Rau AG of Germany, GT Solar of USA, Herbert Arnold GmbH & Co. KG of Germany and RENA GmbH of Germany. The manufacturing facility will be for 60 MWp (megawatt peak) of multi-crystalline solar photovoltaic cells and fabrication of 125 MWp multi-crystalline silicon wafers using solar grade silicon. Phase I is slated to be commissioned by December 2011.
Phase I of the project will entail an investment of Rs 1,493 crore which is to be funded through a debt of Rs 970 crore. Asia Pacific Capital will invest $15 million (approx Rs 68 Crore) as private equity in the project.