Yamuna International Airport achieves financial closure for Noida International AirportIllustrative image – not actual.
The Yamuna International Airport (YIAPL), a fully-owned subsidiary of Zurich Airport International, which is developing the Noida International Airport in Uttar Pradesh, has achieved financial closure for the airport project. 
 
On 10 August 2021, YIAPL signed the financing agreements with the State Bank of India (SBI) and the Noida International Airport (NIAL) to achieve financial closure of the Noida International Airport (NIA) project. 
 
YIAPL has raised Rs 3,725 crore in debt from SBI to be repaid over a period of 20 year with one-year moratorium post completion of the JewarAirport project. 
 
This is one of the largest financings in an Indian greenfield airport. The financial closure marks another crucial milestone for the project, bringing it closer to the start of construction works. 
 
The date on which financial closure is achieved is usually deemed to be the date of commencement of concession period. Phase-I of the airport is due to be operational by 2023, and will handle 12 million passengers per year. 
 
Zurich Airport has earlier pipped three bidders -- the GMR Group-led consortium comprising Delhi International Airport (DIAL), Adani Enterprises and Anchorage Infrastructure Investments Holdings Ltd -- by offering the highest bid for the airport project. 
 
The Jewar Airport will be the NCR’s third airport, after the Indira Gandhi International Airport (IGIA) and Ghaziabad’s Hindon. 
 
Phase-II of the airport is due to be completed by FY31 and will increase its capacity to 30 million passengers per year, while Phase-III and Phase-IV are due to be finished by FY36 and FY40, respectively, further enhancing its capacity to 50 million and 70 million passengers, respectively.