Illustrative image – not actual.Delhi government's Yamuna Bridge project is likely to be awarded by December 2006, highly placed officials told ProjectsToday. Delhi Tourism & Transport Development Corporation, the project implementing agency, is currently short-listing contractors for the project.
Discussing the current project status, DTTDC officials said that all major approvals and clearances were in place. These included approvals from Delhi Development Authority, Yamuna Committee and Airports Authority of India.
The corporation has appointed Germany-based Schlaich Bergermann & Partners as consultants for the main bridge project, while Systra SA of France has been retained for the approach road segment. The detailed project report is likely to be completed by end of 2006.
DTTDC expects work on the Rs.460 crore project to begin in February 2007 for completion within three years thereafter.
Yamuna Bridge Project: The Yamuna Bridge (also known as the Signature Bridge) is proposed to come downstream the existing bridge-cum-barrage at Wazirabad and will connect NH-1 (Road No.50) on western bank and Wazirabad Road (Road No.59) on the eastern bank of the Yamuna. The bridge is the first of its kind in Delhi and will have a nearly 175-metre-high bow-shaped pylon with cable stays on one side and back stays on the other side. The total length of the proposed bridge, along with the approach spans, would be 575-600m. The signal-free approaches will be constructed from the eastern side (Khajuri Khas) and the western side (NH-1) so as to improve traffic circulation on two sides of the Yamuna River near Wazirabad and the adjoining area.
The pylon will have two-level viewing galleries and deck at top with a provision of two lifts for carrying tourists. The bridge would also have pedestrian sub-ways and footpath and lower level road.