Illustrative image – not actual.Wrench Solutions, a provider of Engineering IT technology solution, will provide WRENCH – an online project control system for Moser Baer Projects’ (MBPPL) coal based power project at Anuppur, Madhya Pradesh.
MBPPL is setting up a 2,520 MW coal based power plant at Anuppur at an investment of Rs 13,700 crore. The power plant is expected to be commissioned in phases by December 2014. The EPC contract for the Phase I of the project has already been awarded to Lanco Infratech and construction at the site has commenced. On completion on MBPPL project, WRENCH is to be implemented on 1,320 MW (2X660 MW) coal based supercritical project in Chhattisgarh.
WRENCH is a software technology that enables real-time project control, collaboration and communication across offices via an online platform that connects all teams, vendors, and shareholders together in real time.