Water Resources Department (WRD), Bihar has issued a tender for the construction of the Barnar reservoir scheme in Jamui district on a turnkey basis. The scope of work includes the construction of a 285-mtrs.-long and 74.31-mtrs.-high concrete dam.
Once completed, the project will provide irrigation to 22,226 ha across the Somo, Jhajha, Khaira, and Gidhaur blocks. The estimated cost of the project is Rs 2,579.37 crore, with a completion timeline of 30 months. The last date for bid submission is 01 July, 2025.
The Barnar reservoir project has faced a delay for nearly five decades. It was originally proposed and approved by the Technical Advisory Committee on Irrigation and Flood Control of the erstwhile Planning Commission in 1975, with an estimated cost of Rs 8.03 crore.