The Western Railway (WR) has chalked out an investment plan of Rs 750 crore to shift the Harbour Line corridor from the east to the west immediately after Mahim station, instead of Bandra, which is the current route.

The proposed move has come in the wake of WR's plans to create additional space to lay more lines for long-distance and local WR trains. It is likely to help WR create space for an ongoing expansion project that involves the laying of a fifth and sixth line between Bandra and Borivali.

The project has been sanctioned under the Phase II of Mumbai Urban Transport Project -II and is now being examined by the Railway Board (RB). It is to be funded by Mumbai Railway Vikas Corporation (MRVC) and to be executed by the WR. Surveys for the project have been on-going for the last two years by Rail India Technical and Economic Services and the first survey has been sanctioned by the RB.

The plan envisages the razing of the flyover at Khar--that transports nine-car Harbour line locals from Khar to Bandra, construction of a new railway flyover starting just after Mahim station and ending near the Mithi River in Bandra. Already, two new additional lines are being laid out across the Mithi. This will now be used exclusively for Harbour line trains. The blueprint calls for an additional fifth and sixth line to the Western corridor, and though housed on the East, they will be segregated from the Harbour line. Finer details of the plans show that the present fifth line that enters the Bandra Terminus will be defunct at a later stage, according to sources.

With the MRVC planning under the Phase II of the MUTP-II to extend the Harbour line to Goregaon, there will be eight lines-an increase of three to four lines-between Bandra and Goregaon. Two will be used for slow trains, two for fast locals, two for Harbour line, and two for long-distance trains.

For the execution of the project, the Harbour and Western lines will exchange sides, and tracks will be pushed aside to make space for the new lines. The expansion also calls for staff residences to be shifted. Staff quarters, which are on the east side of existing tracks at Vile Parle, Santa Cruz and Dadar, will be brought down and they are likely to be shifted to a highrise in Dadar.