World Bank to fund road projects in UPIllustrative image – not actual.

The World Bank has agreed to fund UP State Road Project II being planned at a cost of Rs.3,000 crore. Of the envisaged cost of $614.84 million (Rs.2,951 crore) World Bank has sanctioned a loan of $488 million (Rs.2,342 crore).

 

The project involves the following work:

  • Construction of Shergarhghat bridge on Yamuna near Mathura
  • Construction of Ghaghra bridge on Sitapur – Baharaich road
  • Construction of Ghaghra bridge on Gorakhpur – Shahganj road
  • Construction of Sharda bridge on Lakhimpur – Belrayan road
  • Construction of Kachhalaghat on Ganga on Barielly – Badaun Road
  • Upgrading 973 km of roads
  • Carrying out major maintenance work on 2,574 km roads
  • Construction of Gora Badshahpur bypass on Jaunpur – Mohammadpur road
  • Construction of Ahirula & Budhanpur bypasses on Gorakhpur – Shahganj road
  • Construction of Bangarmau bypass on Katra – Bilhaur & Lucknow – Bangarmau roads

 

The state has also received aid for UP Diversified Agricultural Support Project, UP Health System Development Project, UP Water Structure Restructuring Project, Power Structure Restructuring Programme, UP Forestry, UP Rural Water Supply & Environmental Sanitation and UP Sodic Lands Project.

 

 

 

 

 

 

 

 

 