World Bank wants the speedy implementation of all schemes being carried out by Mumbai Urban Transport Project (MUTP).

A World Bank team is visiting India for fortnight-long bi-annual review mission. As per the review, the bank expects the Jogeshwari-Vikhroli Link Road (JVLR) to be completed by end 2009 and it has agreed to provide increased supervision of the project for the remaining period. The other project like Kurla-Thane line new corridor work will also be completed by end 2009. The delivery of modern high speed rakes is to be completed by June 2010 at the rate of four per month till March 2009 and then six per month.

The central government request for the extension of the loan period of MUTP projects till 31 December 2009 is being considered by the bank.The mission will now again come in January 2009.

 

 