Works in full swing at Balanagar flyover in HyderabadIllustrative image – not actual.

The Hyderabad Metropolitan Development Authority (HMDA) is speeding up works at Balanagar flyover in Hyderabad, Telangana. All efforts are being made to commence operations on the flyover by August 2020.

 

Work on the flyover was dragging on due to delay in land acquisition, traffic regulation and other reasons. Now, with the Greater Hyderabad Municipal Corporation (GHMC) almost completing the land and property acquisition and demolishing 357 structures, HMDA is executing the civil works on a war-footing.

HMDA has completed foundation and pillar works and is now taking up slab and ramps works. Generally, it takes about 10 days for completing works pertaining to one foundation but during the lockdown, HMDA has managed to complete seven foundations in about 30 days.

Right from pillars to slabs, these works will be executed in precast method to complete at the earliest. HMDA is constructing the 1.13 km flyover at a cost of Rs 387 crore. Of this, Rs 265 crore is earmarked for land acquisition and the rest for civil works.

The six-lane flyover will be 24 mtr wide. The carriageway beneath the structure is also being widened from 30 mtr to 45 mtr to facilitate smooth flow of traffic.