Work underway on Sangamnath Sugars’ upcoming manufacturing unitIllustrative image – not actual.
Sangamnath Sugars is setting up a sugar manufacturing unit at Byalihal in Vijayapura district of Karnataka.

Phase-1 of the project will have a capacity of 3,500 tccpd and also include co-generation power unit with a capacity of 20 MW.

The project will see an investment to the tune of Rs 233 crore. It will create employment opportunities for 340 to 450 persons.

In October 2018, land was acquired and financial closure was underway.

Work on the project began in January 2019. As per the latest update available with Projects Today, around 50 percent financial closure has been achieved. Work is underway with completion scheduled for October 2020.