The Electricity Supply Corporation of Malawi (ESCOM) has awarded key contracts for the construction of the 218 km Malawi-Mozambique Interconnector Project and Matambo Substation as part of the Mozambique-Malawi Interconnection Project (MOMA).

The transmission line and expansion of Phombeya will be built by L&T India, while the Matambo Substation Upgrade will be built by Sino Hydro of China, with both projects being managed by Gopa Intec International of Germany.

The project would now be completed in October 2023 rather than December 2022 as scheduled due to Covid-19, which delayed work and organization.

The MOMA initiative is supported by the World Bank, the European Union through KfW, and the Malawian government through ESCOM. The project is valued at USD 127 million. Once completed, it will provide 50 MW to the country’s electrical grid.