Illustrative image – not actual.The project will also include extension of runway including resurfacing of flexible portion of runway, taxiway, construction of new terminal building, ATC tower-cum-technical block, fire station, apron extension, drainage works, boundary wall and other associated works along with electrical works.
The proposed terminal building with an area of 9,350 sq mtr will be built with eco-friendly sustainable material and equipped with solar photovoltaic system and energy-efficient equipment.
Stup Consultants is the project management consultant. In March 2016, the terms of reference (ToR) was granted for the airport expansion project.
In February 2018, Vishal Infrastructure bagged an order worth Rs 122.06 crore for upgradation of the project to make it suitable for operation of AB-320 type of aircraft includes extension of runway, construction of new apron, taxi track and other works.
In August 2018, Union Minister of Commerce and Industry and Civil Aviation Suresh Prabhu laid the foundation stone for the project. In May 2019, the Union Ministry of Environment, Forest and Climate Change (MoEF&CC) accorded environmental clearance (EC) and in the same month the work also commenced on the project.
In May 2019, NKG Infrastructure bagged order Rs 140.49 crore for construction of a new terminal building, ATC tower-cum-technical block, fire station Category VII and other building associated works of the project.
As per the latest information available with Projects Today, work on the order bagged by NKG Infrastructure is underway. The entire project will be completed by February 2020.