Work underway on four-laning of Akkalkot-Solapur sectionIllustrative image – not actual.
G R Infraprojects, the concessionaire, has undertaken four-laning of Akkalkot-Solapur road section in the state of Maharashtra.

The four-laning has been undertaken from Akkalkot at 99.40 km to Solapur at 138.35 km section of NH-150 (extn) along with Akkalkot bypass on hybrid annuity mode (HAM).

The tender for undertaking the project was invited in 2017. However, the tenders got re-invited and extended many times. G R Infraprojects was appointed as contractor for development of the project on March 2018 and work began in November 2018. The project was estimated to be completed by November 2020.

The estimated cost of the project is Rs 807 crore.

As per information available with Projects Today, around 43 percent work has been completed. The project is expected to be completed by the end of May 2021.