Illustrative image – not actual.The project will be implemented by phases manner and will be funded partly under JNNURM. The detailed project report (DPR) for the project was prepared by National Highways Authority of India.
Dilip Buildcon was appointed as the contractor for the project in December 2016. The foundation stone for the project was laid by Chief Minister of Andhra Pradesh N Chandrababu Naidu in June 2017.
As per the information available with Projects Today, around 65 percent work on the project has been completed with completion scheduled for September 2019.