Illustrative image – not actual.Beekaylon Synthetics is setting up a polyester yarn manufacturing unit with a capacity of 20,000 tpd at Velugam village in Dadra & Nagar Haveli.
The project will come up over 53,000 sq mtr of land and will be implemented in three phases. The project will see an investment to the tune of Rs 150 crore. Siddheshwar Infra, Gujarat was appointed as the contractor for the project. Work on the Phase-I of the project has been completed.
As per the latest update available with Projects Today, work on the Phase-II and III is likely to commenced by November 2019.