Illustrative image – not actual.The expansion work of Century Textiles & Industries paper facility at Nainital in Uttaranchal is scheduled to commence by July 2007.
The expansion work of Century Textiles & Industries paper facility at Nainital in Uttaranchal is scheduled to commence by July 2007.
Century Textiles plans to expand capacity of its paper manufacturing facility at Lalkua near Nainital by installing a 211 tpd paper plant. It would entail an investment of Rs.385 crore. The capacity of the paper would be increase by 75,000 tpa from its existing level of 37,250 tpa. It would also include 16 MW bagasse based power unit. Avant Garde, Chennai is the consultant for the power plant.
Work on power plant is nearing completion with completion scheduled end-January 2007.