Illustrative image – not actual.Dhamra Port is expecting to commence work on its Phase II expansion by 2015 among speculation over stake sale by the port promoters-L&T and Tata Steel and also prevailing uncertainty over land allotment.
The Rs 10,000-crore Phase-II expansion of the port will add 75 million tonne capacity which from the port's existing capacity of 25 million tonne. The environmental clearance for the project is in advanced stage. The additional allotment of land to DPCL for phase II development will be considered by the state government on the basis of some norms (thumb rule) being formulated. Also, the state commerce & transport department had stipulated terms which DPCL needs to comply for being eligible for additional land. These are as follows:
- The port has to achieve capacity utilization of 70 per cent of Phase-I in accordance with clause 4.4 of the concession agreement.
- It has to obtain environment clearance from Union ministry of environment & forests (MoEF) for the proposed expansion.
- DPCL also has to get a no-objection certificate from the National Green Tribunal in the matter of expansion of port beyond the limits of the port.
Currently, the company have two berths at the Dhamra port and full scale expansion will raise the berth strength to 13. Once work on the project starts it is expected to commission in five years.
Post expansion, the port will be able to handle container cargo, liquid cargo, LNG (liquefied natural gas) and crude oil.