Illustrative image – not actual.Water Resources Department, Gujarat, is planning to lay pipelines for the Saurashtra Narmada Avtaran Irrigation (SAUNI) scheme, in July 2014.
The entire pipeline-based project envisages supply of surplus Narmada water to the 115 irrigation dams of all the seven districts of Saurashtra, at an estimated investment of Rs 10,000 crore.
It will be implemented in three phases. In Phase-I, the pipeline will be connected to 40 dams and is expected to be completed in 2016.
Work is moving at a fast pace. The department will start by linking four major projects of Saurastra first.
The four projects identified for linking are: Macchu-2 in Morbi and Und-1 in Jamnagar that will be connected with a 57 km long pipeline. The second one is Limbdi Bhugau-2 in Surendranagar with Bhimdod in Bhavnagar with a 51 km long pipeline. The third one is Wadhwan Bhugau-2 in Surendranagar with Macchu-1 in Morbi with a 66 km long pipeline, and the fourth is Limbdi Bhugau-2 in Surendranagar with Ankadiya, in Rajkot with a 54 km long pipeline.