Work progresses on Mysuru-Kushalanagar NH projectIllustrative image – not actual.

The development of the Mysuru-Kushalanagar National Highway is gaining momentum as the access-controlled highway project moves forward. The Ministry of Road Transport and Highways (MoRTH) has approved a total project cost of Rs 4,129 crore for this 92.3-km highway.

The completion is expected by June 2027, reducing travel time between Mysuru and Kushalanagar to approx. one to 1.5 hours. Additionally, the travel time between Kushalanagar and Bengaluru is projected to decrease to three to 3.5 hours, boosting economic activities in the region, including between Kodagu, Mysuru, and Bengaluru.

As of now, around 80 percent of the land required for the greenfield project has been acquired. Discussions are ongoing with the forest department for clearances to proceed with works in forest areas. The four-lane access-controlled highway will begin at Paschimavahini near Srirangapatna and terminate at Guddehosur in Kushalnagar, Kodagu district. The right of way (RoW) varies between 45 mtrs. in urban areas and 60 mtrs. in rural areas.

The project's construction is divided into four packages, with Package-I from Paschimavahini to Guddehosur and Packages-II, III, and IV covering segments between key junctions. For Package-II (Guddehosur-Kushalnagar bypass), 82 percent of the required land is already in possession, while Package V (Ramanathapura Terakanambi Road, KR Nagar Junction to Yalachahalli) also holds the same extent of land. Package-III, connecting Hemmige village to the Hassan-Periyapatna Road junction, has 80 percent of its 136 hectares of land acquired, and Package-IV, between Ramanathapura Terakanambi Road and Yalachahalli, has 70 percent of its 161.8 hectares acquired. 

← All latest storiesBack to top →