Work ongoing on two-laning of Gharghoda-Lailunga RoadIllustrative image – not actual.
The Chhattisgarh Road Development Corporation has undertaken two-laning with hard shoulder of Gharghoda-Lailunga Road from the existing chainage 0.00 km to 22.71 km (design chainage from 0.00 km to 22.68 km) in Chhattisgarh on EPC basis.

The project comprises the following works -- B T works 16.75 km, W M M 16.75 km, J S B 16.75 km, subgrade 16.75 km, seven minor bridges and 23 culverts.  

The cost of the project is Rs 73.48 crore. The request for proposal (RfPs) from contractors for the project was invited in September 2016 and subsequently in February 2017, Shree Balaji Engicons in JV with Sunil Kumar Agrawal bagged an order to execute the project.

As per the latest update available with Projects Today, B T works was completed on five km, W M M work was completed on nine km, J S B on nine km, subgrade on 16 km, four minor bridges and 19 culverts have been completed.

The project is expected to be completed by the end of 2019.