The strategic Zojila tunnel project, between the Kashmir valley and the Ladakh region, is witnessing a rapid pace in the execution of work. Over 40 percent of the drilling has been completed, and the project is expected to be completed by December 2026.
Megha Engineering and Infrastructure (MEIL) is constructing the single-tube tunnel through the Zojila Pass at an altitude of 11,578 ft. on the Srinagar-Kargil-Leh National highway. MEIL is deploying the new Austrian tunnelling method, and once completed, the tunnel would also be the longest in Asia at the highest altitude.
As per plan, the 13 km-long tunnel will run from Baltal, in the Ganderbal district of Central Kashmir, to Minimarg, in Drass town of Kargil district of Ladakh. A total of 6 km cutting has been done.
The total length of the project from Sonamarg to Minimarg is 31 km. From Sonamarg to Baltal is an approach road of 18 km, and then the main tunnel from Baltal to Minimarg which is 13 km long. The work is underway simultaneously on the approach road of 18 km.
About 60 percent of work has been completed on this, while there are four bridges on which about 80 percent of the work is completed. There are five-km Nilgarh tunnels which have been completed. The approach road would be operational within two years.
When constructed, the tunnel will enable the Indian defence forces, and people of J&K and Ladakh to move uninterrupted throughout the year in this region. Moreover, the distance will be covered in under 40 minutes instead of four hours.
The project gains prominence as normally, the highway remains closed during winters due to heavy snowfall, which cuts off Ladakh region from Kashmir.