Illustrative image – not actual.Work on the proposed Worli-Haji Ali section of the Worli-Nariman Point Freeway Project to be executed by MSRDC is likely to commence in December 2010.
The bridge spanning 3.30 km is to entail a cost of Rs 1,950 crore.
Arup-CES (JV) was preparing the contract agreement while the concession agreement was likely to be signed soon. MSRDC is likely to achieve financial closure by end-2010.
Meanwhile the detailed feasibility study for the Haji Ali-Nariman Point section was underway. Topographic survey, bathymetric survey and geotechnical report is to be completed by November 2010 while a preferred bidder will be selected by July 2011.