Illustrative image – not actual.The steering committee of the Kerala State Transport project (KSTP-II) has decided to call for a re-tender for the bypass in the Chengannur-Ettumanoor stretch.
The project was awarded to EKK and Company without completing land acquisition procedures. It could not be executed due to unrealistic DPR. Due to this, construction of a flyover was considered to be more feasible against this backdrop.
The original cost of the project was Rs 31.8 crore for construction of the 2.3 km bypass. Construction of the flyover itself is expected to cost an additional Rs 37 crore.
The project was launched in 2014 without acquiring half of the land required for construction.