Work on the Ega-Valluvar flyover to begin Illustrative image – not actual.

Work on the Ega-Valluvar flyover will start with the widening of Valluvar Kottam High Road from the Nungambakkam High Road junction upto Independence Day Park.

 

This 2.76 km flyover  will connect Ega Theatre to Valluvar Kottam in just two minutes and cut down travel time. The total estimated cost of this flyover project is Rs 1,100 crore. It is projected to be completed in three phases, with each taking a period of six months. Work on the double flyover at Valluvar Kottam will begin after the road widening.

 

It will require 38,000 sq mtr of land for construction of the flyover. From which, 27,000 sq mtr of land has to be acquired from private land owners at a cost of Rs 750 crore to the corporation.

 

The project will be completed by 2016.

 

More Project Info:

Flyover (Ega-Valluvar) Project

 