Illustrative image – not actual.The project entailing an investment of Rs 365 crore will include products like mild steel billets with a capacity of 3,24,000 tpa, TMT bars/structural steel with a capacity of 3,00,000 tpa, ferro silicon with 8,400 tpa capacity, among others.
The project will generate employment for 350 persons during operation.
In February 2020, Sugna Sponge & Power submitted Form 1 and pre-feasibility report for grant of terms of reference (ToR) for the project.
As per information available with Projects Today, work is expected to commence by October 2020. The completion is slated for December 2021.