Illustrative image – not actual.According to Mr J. Parthasarthy, chairman and managing director of AP Genco, work on 420 MW Rayalaseema Thermal Power Project (RTPP) II at Muddanur in Cuddapah district of Andhra Pradesh, will commence in the first quarter of 2002.
Recently, a team of officials from the EXIM Bank and the
China National Machinery & Equipment Import & Export Corporation were
in Hyderabad to discuss the bank guarantee format for the power project.
The project envisages setting up two units of 210 MW
each at an estimated cost of Rs.1,578 crore.
The plant will operate on washed coal sourced from the IB Valley block of
Mahanadi Coalfields in Orissa. The
first unit is scheduled for commissioning within 31 months from zero date and
the second unit, three months later.
