Illustrative image – not actual.
Work on the 11.5 km underground section of the Regional Rapid Rail Transit System (RRTS) corridor spread across Delhi, Ghaziabad and Meerut is expected to begin within two months.
The underground tunnel will be laid from New Ashok Nagar in Delhi up to Sahibabad, covering about 4.5 km, while the remaining will be in Meerut. The National Capital Region Transport Corporation (NCRTC) has already started assembling machines for the tunnel work at the proposed sites.
In Delhi, the tunnel will start near New Ashok Nagar covering a distance of about 2.5 km till Anand Vihar, two km on the Ghaziabad side from Kaushambi to Sahibabad near Country Inn Hotel and around seven km in Meerut from Bhaisali to MES Colony.
The launching shafts are about 20 mtr deep and 16 mtr wide. Two tunnel boring machines (TBMs) will be lowered in these shafts to bore the RRTS twin tunnels from Anand Vihar towards Sarai Kale Khan. It will be the longest tunnel section between any two stations.
Apart from this, on the 17 km Sahibabad to Duhai section, the tunnelling work is on and trial is expected to begin by the middle of 2022.