Work on New Legislative Assembly Complex continues without approvalIllustrative image – not actual.

Jammu and Kashmir Projects Construction Corporation (JKPCC) is carrying out work on the New Legislative Assembly Complex at Jammu without obtaining approval on cost from the Planning and Development department of the state.

Work on the six storey assembly complex covering 70,000 sq ft has been going on for the past five years.

The project has missed several deadlines due to lack of funds, and now the proposal has been sent to the cabinet for approval to allocate the required funds.

The project was taken up by the company in May 2011, with completion scheduled in three years. However, it was extended to March 2015. Less than 40 percent work has been completed on the project so far.

The initial cost of the project was Rs 104 crore, to be shared by State and Central governments equally. The central government has funded Rs 58 crore for the project, while the state government will fund the remaining amount.

The project was expected to cost Rs 199 crore, but was recently finalised at Rs 166 crore.

 