Work on Nanjundapuram flyover to be completed soon Illustrative image – not actual.

Work on the bridge across the railway line on Nanjundapuram road, in Coimbatore district of Tamil Nadu, is likely to be completed by end July 2014.


The project, worth Rs 12.6 crore, undertaken by Tamil Nadu State Highways Department, includes construction of a 693 mtr, two-lane bridge. It includes 337.75 mtr road on the Ramanathapuram side and 317.26 mtr road on the Podanur side.


All work related to the bridge has been completed, and the 150 mtr road on one side and 90 mtr on the other is yet to be done.


The project has been facing delay for more than two years.


It has been learned that the state highways department is looking to cancel the contract if work on the project is not completed by the end of July 2014. The work was expected to be completed by December 2013.