The Bangalore Metro Rail Corporation (BMRCL) has not been able to connect the northern corridor of Namma Metro to the city’s centre as work on the crucial 800 mtr stretch between Sampige Road to Majestic Metro station is under progress.

BMRCL is preparing to lay tracks in one of the tunnels (Margarita), while dismantling of the Godavari TBM in the other tunnel is almost over. BMRCL needs about three months to lay tracks till the Majestic Metro station from the northern side.

At present, BMRCL is dismantling the giant Kaveri TBM (southern side), which is expected to take two months. The corporation will be able to take up signalling work on the entire underground stretch only after completing the track laying work

Commercial operations on the entire North-South Corridor connecting Puttenahalli in the south to Nagasandra in north Bengaluru via Majestic might begin from November by using a single line.