Illustrative image – not actual.MahaMetro is planning to start work on Nagpur Metro Phase-II in June or July 2021, well before the completion of Phase-I, which is scheduled in December 2021.
The allocation for Phase-II has been made in the Union Budget for 2021-22 even though it has not been cleared by the Cabinet yet.
The Union Ministry of Housing and Urban Affairs (MoHUA) has already cleared Phase-II. It had sent copies of the detailed project report (DPR) to other concerned ministries like finance, road transport, railways, home, environment, etc.
MoHUA will then prepare a detailed note for the cabinet and submit the DPR to it for approval.
MahaMetro will secure finance from foreign agencies immediately after the Cabinet approval and then float tenders for all four reaches of the Phase-II. For Phase-I, tenders for the four reaches were floated one after another. Phase-II has a length of 43.8 km with 32 stations.
The corridors include one from Automotive Square to Kanhan – 13 km length and 12 stations. The corridor will cater to areas like Khasara, Lekha Nagar, Kamptee and Dragon Palace.
The second corridor will be from Mihan to Butibori MIDC ESR – 18.7 km length and 10 stations. The corridor will have the catchment area of Jamtha, Dongargaon, Mohgaon, Butibori, Mhada Colony and Indorama Colony.
The third corridor is from Prajapati Nagar to Transport Nagar – 5.5 km length and three stations. The corridor will cater to areas in the vicinity of Ambe Nagar, Kapsi, Transport Nagar and Asoli.
The fourth corridor is Lokmanya Nagar to Hingna – 6.6 km length and seven stations. The corridor will pass through Nildoh, Gajanan Nagar, Rajiv Nagar, Lakshmi Nagar, Raipur, and Hingna village, including surrounding MIDC areas.
The viaducts will be built on the median of roads and the area of land required to be acquired for Phase-II is one-tenth of the first one.
The cost of Phase-II is Rs 6,708 crore. The contribution of the government of India (GoI) and the government of Maharashtra (GoM) is Rs 998.2 crore each.
In addition, both will pay Rs 197 crore as subordinate debt towards central taxes. The foreign loan component is Rs 3,585.60 crore. The remaining amount will be paid by the Maharashtra Industrial Development Corporation (MIDC) and the Maharashtra Airport Development Company (MADC).
The allocation for Phase-II has been made in the Union Budget for 2021-22 even though it has not been cleared by the Cabinet yet.
The Union Ministry of Housing and Urban Affairs (MoHUA) has already cleared Phase-II. It had sent copies of the detailed project report (DPR) to other concerned ministries like finance, road transport, railways, home, environment, etc.
MoHUA will then prepare a detailed note for the cabinet and submit the DPR to it for approval.
MahaMetro will secure finance from foreign agencies immediately after the Cabinet approval and then float tenders for all four reaches of the Phase-II. For Phase-I, tenders for the four reaches were floated one after another. Phase-II has a length of 43.8 km with 32 stations.
The corridors include one from Automotive Square to Kanhan – 13 km length and 12 stations. The corridor will cater to areas like Khasara, Lekha Nagar, Kamptee and Dragon Palace.
The second corridor will be from Mihan to Butibori MIDC ESR – 18.7 km length and 10 stations. The corridor will have the catchment area of Jamtha, Dongargaon, Mohgaon, Butibori, Mhada Colony and Indorama Colony.
The third corridor is from Prajapati Nagar to Transport Nagar – 5.5 km length and three stations. The corridor will cater to areas in the vicinity of Ambe Nagar, Kapsi, Transport Nagar and Asoli.
The fourth corridor is Lokmanya Nagar to Hingna – 6.6 km length and seven stations. The corridor will pass through Nildoh, Gajanan Nagar, Rajiv Nagar, Lakshmi Nagar, Raipur, and Hingna village, including surrounding MIDC areas.
The viaducts will be built on the median of roads and the area of land required to be acquired for Phase-II is one-tenth of the first one.
The cost of Phase-II is Rs 6,708 crore. The contribution of the government of India (GoI) and the government of Maharashtra (GoM) is Rs 998.2 crore each.
In addition, both will pay Rs 197 crore as subordinate debt towards central taxes. The foreign loan component is Rs 3,585.60 crore. The remaining amount will be paid by the Maharashtra Industrial Development Corporation (MIDC) and the Maharashtra Airport Development Company (MADC).