The Brihanmumbai Municipal Corporation (BMC) has completed 40 percent physical work of the Mumbai Coastal Road project, including a one-km-long tunnel. The project will be completed in November 2023. The project is worth Rs 12,000 crore from Marine Drive to Worli.
The work completed so far includes a tunnel of onekm length and 40 ft diameter under the Malabar Hill in south Mumbai. Only work on 900 mtr of the tunnel is remaining now.
It is the first-of-its kind under-sea tunnel project of 40 ft diameter executed in the country. The project being executed by BMC between Marine Drive and Worli is 27 km long and includes 16 km long interchanges.
The coastal road would also include a 125 acre garden on reclaimed land abutting the freeway besides arrangements for underground parking for 1,852 cars.
The project to be taken up in two phases, which was launched in around the beginning of the COVID-19 lockdown in early 2020, is proceeding round-the-clock in three shifts to catch the November 2023 deadline.
The project execution was scheduled to start in October 2018 with a completion date of end-2022, but got bogged down in litigations, a stop work by the court in July 2019 as the CRZ clearances were quashed.
The work resumed on the project only after the Supreme Court stayed the Bombay High Court orders in December 2020 and is now proceeding at a quick pace in Phase-I.
The civic body has envisaged the Mumbai Coastal Road project along the western seafront of the city to decongest the existing roads.
In Phase-I, this eight-lane project intends to connect Shamaldas Gandhi Marg (Princess Street Flyover, Marine Drive) in south Mumbai to the Worli-end of the Bandra-Worli sealink, comprising a combination of coastal road based on reclamation, tunnels, flyovers, elevated roads, interchanges and sea wall/break wall.
India's largest 12.19 mtr diameter tunnel is being constructed 20 mtr below the shore of the Arabian Sea and 70 mtr below the Malabar Hill and has three lanes for transportation for south- and north-bound traffic. One of the lanes is proposed to be reserved for emergency transport.
The objective of this project is to provide an alternate North-South Trunk route for the people of Mumbai which provides improved mobility to relieve traffic congestion in Mumbai, enhances environment and leads to sustainable development of much needed recreational public open spaces.