Illustrative image – not actual.
The work on the eight-lane Mumbai Coastal Road project is now 17 percent complete on the southern side from Marine Drive to Worli and the section is expected to be operational by July 2023.
Substantial work has been completed in the past couple of months spending Rs 1,281 crore till November 2020.
The work, which proceeded in full swing during the lockdown months, involved reclaiming 175 acre land from the Arabian Sea, while another 102 acre is currently being reclaimed.
A highlight of the project will be 400 mtr long and 39.60 ft diameter tunnel boring machine (TBM), which has been fully assembled. It will now be deployed for tunneling work on the Girgaum Chowpatty-Malabar Hill sector for 3.40 km long double-tunnel, starting from 7 January 2021.
The project worth Rs 12,721 crore when fully completed will connect Churchgate with Kandivali, which will allow vehicles to move at higher speeds, significantly reducing travel time between the two points, and also the Mumbai Airport.
The work on the Brihanmumbai Municipal Corporation's eight-lane road project, running 29.20 km of west coast of Mumbai, commenced in October 2018 with a completion target of 2022. However, the project got delayed owing to litigations.
The work halted in July 2019 when the Bombay High Court quashed the Coastal Regulation Zone (CRZ) clearances given to the project. The work resumed after the Supreme Court stayed the High Court order in December 2019.