The JV partners, who have received the work order for the project have already deposited the necessary performance guarantee amount with Rail Vikas Nigam (RVNL), clearing the way for the work to start by July 2014.
The project will be undertaken at a cost of Rs 817 crore, of which two-thirds of the cost will be borne by the state government.
The major work under phase-II of the project will include airport connectivity from Falaknuma-Umdanagar to the Shamshabad airport, doubling and electrification of the Sanathnagar-Moula Ali line, quadrupling of the Moula Ali-Ghatkesar line, doubling and electrification of the Moula Ali-Malkajgiri-Sitafalmandi line and the Bolarum-Medchal line, electrification and remodeling of the Secunderabad-Bolarum line, and restoration of the Telapur-Patancheru track.
Except for the work in Falaknuma-Umdanagar-Shamshabad (airport connectivity) stretch, for which tenders are yet to be invited, work in all other corridors are going to be taken up simultaneously under three different packages.
Related Link:
Project Profile