Work on MG Petrochem’s grain-based distillery unit progressing wellIllustrative image – not actual.
MG Petrochem is setting up grain-based distillery unit with a capacity of 215 klpd in Panchkula district of Haryana. 
 
The project will also include a six MW co-generation power plant. In the Q3/FY22, the Ministry of Environment, Forest and Climate Change (MoEF&CC) accorded environment clearance (EC) for the project, following this work on the project began in 2022. 
 
As per the information shared with Projects Today, around 80 percent work on the distillery unit has been completed. The project is expected to be completed by the beginning of 2023.
← All latest storiesBack to top →