Work on metro VAG line stations in full swingIllustrative image – not actual.

The construction work of Ghatkopar station on Versova-Andheri-Ghatkopar (VAG) metro line is in full swing.

At present, balance main building 1st concourse slab work, track level and available platform level slab and utility building slab work is in progress.

As per the report prepared by Louis Berge Group Inc, at Versova station, concreting of seven spine beams and three transverse beam is completed and two transverse beams’ work is in progress. At DN Nagar station, concreting of five spine beams is completed and median column and other spine beams’ work is in progress. At Azad Nagar Station, concreting of five spine beams is completed and concreting for nine transverse beams is in progress.

At Andheri station, main building slab wok is in progress whereas at WEH station, pile cap, side columns and side 1st concourse slab work is in progress. Similarly, at Chakala, Airport Road and Marol Naka stations, concourse slabs are completed. At Saki Naka station, balance piling work and median column work is in progress.

Related Links:
Project profile

← All latest storiesBack to top →