Illustrative image – not actual.Mumbai Metropolitan Region Development Authority (MMRDA) is likely to commence construction work on Phase-II of the Marine Drive beautification project in December 2014.
Due to the election code of conduct and the pending clearances from other agencies including the Ministry of Environment and Forests, MMRDA is planning to invite bids for the project in July 2014. It will require three months to finalise the bids and award the work order.
The project, estimated to cost Rs 78 crore, is expected to be completed by June, 2015. It involves development of a viewing balcony, amphitheatre, and the restoration of Parsi Gate, which is diagonally opposite Taraporewala Aquarium.
Phase-I of the project was commissioned in August 2008, with an investment of Rs 130 crore. It included a facelift of the Queen's Necklace by strengthening the promenade walls and reworking the landscaping, among other things.
Related Link:
Project profile