Illustrative image – not actual.The work on the grade separator project proposed by the Bangalore Development Authority (BDA) at the Outer Ring Road (ORR) and Hosur Road (NH-4) intersection near Central Silk Board in Madiwala in Bangalore is expected to start in April 2002 and be completed within two years.
The grade separator project is estimated to cost Rs.25 crore. The Rail India Technical and Economic Services (RITES) has already prepared the detailed project report, while the initial work for formulating the tender guidelines has already commenced.
The proposed grade separator would have a 10.5 mts
wide main ramp, with four lanes (one-way) along NH-4 crossing the ORR and
lifting traffic plying from Bangalore to Hosur, while vehicles plying from
Hosur towards Bangalore would use the existing surface road. For vehicles taking
a right turn towards BTM Layout (ORR) from NH-4, an up-ramp of 7.5 mts wide
would be provided, while vehicles taking a right turn from BTM Layout (ORR) to
Hosur Road, a Clover Leaf ramp of 7.5 mts has already been provided.
An independent ramp of 7.5 mts wide would be provided for traffic moving
towards Koramangala from Hosur Road to avoid congestion at the Madiwala
junction near the police station. Service roads of 7.5 mts wide would be
provided along the grade separator for free left turn and local traffic.
However, right turn for vehicles from Koramangala side to Madiwala would not be
allowed.
The grade separator is the first in the series of projects being taken up by
the BDA with the objective of improving the city’s infrastructure. BDA has
pledged to develop infrastructure projects worth Rs.150 crore in the next two
years.
The BDA is also engaged in executing grade separator and flyover projects along
the ORR stretch at Benniganahalli, Whitefield and Hebbal lake. All these are