Work on Karanpur-Rudrapur/Pantnagar pipeline commencedIllustrative image – not actual.

GAIL India on 22 October 2010 commenced construction of its Karanpur- Moradabad-Kashipur-Rudrapur/Pantnagar natural gas pipeline.

The pipeline will be 182 km in length. The pipeline will pass through Badayun and Moradabad districts in Uttar Pradesh and Udham Singh Nagar in Uttarakhand. The design capacity of the pipeline will be 2.5 mmscmd.

The line will be built in two phases. In Phase I, 101 km of the pipeline will be laid from Karanpur to Kashipur. It is to be completed by January 2011.

Phase II of the project will consist laying a 58 km pipeline from Kashipur to Rudrapur/Pantnagar. This phase is slated to be completed by January 2012.