Work on Karad distillery project nears completionIllustrative image – not actual.

Yashwant Rao Mohite Krishna SSK's distillery expansion project at Karad in Satara district of Maharashtra is nearing completion. The company is expanding the capacity of distillery from 75 klpd to 95 klpd.

The project will also include 32 MW (2x16 MW) co-generation power unit, to be set up in two phases. Each phase will comprise of16 MW power unit, of which around 12 MW of power unit will be sold.

Thermax, Pune and T D Power System, Bangalore has been finalised as machinery suppliers for the project.

Work on the distillery unit is scheduled for completion by October 2008, whereas, civil works on the power unit is completed and machinery erection is expected to commence soon. The power unit will commence operations by October 2009.