Work on Kaladan multi-modal transit transport project to complete soonIllustrative image – not actual.

A cross-border road under the Kaladan multi-modal transit transport project (KMTTP) which is being developed by Mizoram Public Works Department (PWD) is expected to be completed by June 2023. The road between Lawngtlai and Zochachhuah is 87.18 km long.

So far, approximately 98 percent of the road component of the Kaladan project on the Mizoram side (NH-501A) and six out of eight bridges have been completed. When completed, the project would connect the eastern Indian seaport of Kolkata to the Myanmar seaport of Sittwe across the Bay of Bengal.

In addition, six more projects are in the pipeline for which the proposal, including a permanent bridge over the Tuivai River to link Mizoram’s northeast with neighbouring Manipur, has been submitted to the Union Ministry of Road Transport and Highways (MoRTH).

Presently, projects worth Rs 2554.98 crores are underway, and include NH-108 (Sairang-New Eden, Tripura), which is 94 percent completed and NH-501A (Lawngtlai-Zochachhuah, KMTTP), and other stretches.

← All latest storiesBack to top →