Work on JSW's Salboni project by JulyIllustrative image – not actual.

JSW Steel reportedly plans to commence work on the project at Salboni in West Bengal by July 2010. Phase I involving an investment of about Rs 12,000 crore is likely to have a capacity of three million tpa. The project is slated to be completed in 30 months.

Work on the project was stalled due to the economic slowdown and a slump in demand for steel in the international market. Threat from Maoists was also one of the reasons for the disruption.

Japan based JFE Steel Corporation is likely to pick up a stake varying between 26 and 40 per cent in the project.

Meanwhile, work on the 800 MW power plant at Ichhapur (near the coal mines) is likely to begin simultaneously entailing an outlay of another Rs 800-1,000 crore.