The work on the Indira Gandhi International Airport’s fourth runway is expected to be completed by the end of October 2021. After it becomes operational, Delhi airport will become India's first airport with four runways.
The new runway is 4,400 mtr long and 75 mtr wide. The third runway 29/11, which runs parallel to the fourth, is a bit bigger.
The new runway is expected to ease the pressure of a likely rise in flight operations. The runway will considerably cut waiting time for flights to land and take off.
This work is part of Phase III-A of the Delhi airport expansion plan. The original deadline for the plan is mid- to the end of 2022. The work on the runway was stalled due to the second COVID-19 lockdown, but picked up from May 2021 onwards.
DGCA will conduct an inspection of the installation of critical equipment such as instrument landing system localiser and CAT-III gear. Another round of inspection will be done after the installation process is complete, after which the go-ahead is likely to be given to start trials.
The trials of the runway could start in November 2021. It is likely that the new runway will be made operational in 2022.