Work on Ind-Barath Energy Utkal Ltd's (IBEUL) 700 MW (2x350) coal-based power plant at Sahajbahal in Jharsuguda district of Orissa is expected to begin by January 2009.

The power plant entailing an investment of Rs.3,150 crore is scheduled to be commissioned by January 2011. IBEUL has achieved a financial closure of Rs.1,181 crore for the power plant. Of the total investment, the equity component is Rs.730 crore while the remaining amount is being raised through debt.

IBEUL is in possession of 423 acre of the total 600 acre needed for setting up the project. The company has appointed an EPC contractor for the project and will install equipment and machinery for the plant in January.

The project has received approval of the state level Single Window Clearance Authority and the company is now awaiting High Level Clearance Authority's approval.

The company has also hired a consultant which is in the process of preparing an environmental impact assessment (EIA) study for the power plant and the EIA report will be submitted soon to the state pollution control board.

IBEUL has secured coal linkage in the Ib valley coalfields, while the Orissa government has ensured availability of water from Mahanadi river.