Work on Gurupriya bridge nearing completionIllustrative image – not actual.
Work on Gurupriya bridge over river Janbai in Odisha is nearing completion. The 910 mtr long bridge is being constructed at a cost of Rs 172 crore.

Kolkata-based Royal Infraconstru is executing the project. Of 910 mtr,  620 mtr deck slab casting has been completed.

Of the 48 pre-stressed concrete girders, the company has already erected 45 and work on the remaining three is in progress. Of the 18 steel girders to be erected in the deep water zone from P11 to P17, erection work of six has already been completed and work on three is underway. Work on the remaining nine steel girders will follow.

Work on the 1,250 mtr approach road on the Papermetla side of the Gurupriya bridge is going on.